At a glance
- Office: Cagayan State University Lasam Campus
- Classification: Highly Technical
- Who may apply: All end-user of purchase request
- Total processing time: 31 days
Requirements
| Requirement | Where to get it |
|---|---|
| Purchase Request | BAC Secretariat |
| Earmarked Purchase Request | Budget Office |
| PPMP | Office of Purchase Request / End-user |
Steps
| What you do | What the office does | Fee | Time |
|---|---|---|---|
| Client submits the properly earmarked purchase request | Organize Pre - Procurement Conference (if necessary). Prepare minutes of the meeting. (BAC Secretariat BAC Office) | None | 4 hours |
| Conduct pre-procurement conference with the members, TWG and end-user (BAC Chair and Members Technical Working Group) | None | 4 hours | |
| Post invitation to bid or request for intent in PhilGEPS and/or in nationwide-circulated newspaper (broadsheet), website of CSU, conspicuous place of CSU. (BAC Secretariat BAC Office) | None | 7 days | |
| Send invitation letters to COA; two non-government organizations; end-users, TWG; and observers. | None | 1 day | |
| Prepare and distribute Bidding Documents. | None | 3 days | |
| Organize Pre-Bid Conference. (BAC Chair and Members Technical Working Group) | None | – | |
| Conduct pre-bid meeting with interested contractors / suppliers / consultants. | None | – | |
| Schedule and organize meeting for the submission and opening of bids. | None | – | |
| Prepare minutes of the meeting. (BAC Secretariat BAC Office) | None | – | |
| Update supplemental Bid bulletin (to be posted in PhilGEPS at least 5 C.D. prior to deadline for submission of bids). After the pre-bid conference, prospective bidders prepare their bidding documents (BAC Chair and Members Technical Working Group) | None | – | |
| Receive SEALED bidding documents from interested bidders marking the date and time they are accepted and logged. (BAC Chair and Members Technical Working Group) | None | 1 day | |
| Conduct opening of bids and bid evaluation. | None | – | |
| Prepare minutes of the meeting. (BAC Secretariat BAC Office) | None | – | |
| Post-qualify the bidder with lowest calculated bid. (BAC Chair and Members Technical Working Group) | None | 2 days | |
| Recommend to the HOPE the award of contract to the bidder with the lowest calculated responsive bid. | None | 1 day | |
| Prepare minutes of the meeting. (BAC Secretariat BAC Office) | None | 1 hour | |
| Approve the Resolution / Issue the Notice of award. (HOPE) | None | 3 days | |
| Contract Preparation and Signing. (HOPE BAC BAC Secretariat) | None | 3 days | |
| Approval of contract of Higher Authority. (HOPE) | None | 3 days | |
| Issue the Notice to Proceed. (Supply Office) | None | 3 days | |
| Post the Notice of Award in PhilGEPS. (BAC Secretariat BAC Office) | None | 1 day | |
| Post the Notice to Proceed and the approved contract in PhilGEPS. | None | – |