Issuance of Development Permit

Registered owners or developers get approval to convert land into a subdivision project.

At a glance

  • Office: City Planning and Development Office
  • Classification: Highly Technical
  • Who may apply: All
  • Total processing time: 19 Days, 5 Hours, 45 Minutes

Requirements

RequirementWhere to get it
Accomplished Application Form for Development Permit (original– 2 sets) *Make sure that the application form is filled out appropriately and duly notarizedCity Planning and Development Office – Zoning Section, Notary Public
Subdivision Development Plan consisting of the site development plan at any of the following scales: 1:200; 1:300; 1:400; 1:600; 1:1,000; or 1:1,200 showing all proposals including the following (2 original / set): 1. Proposed lay-out of streets, lots, parks and playgrounds and other features in relation to existing conditions 2. Roads, easements or right-of-way and road width, alignment, gradient and similar data for alleys, if any. 3. Lot numbers, lines and areas and block numbers. 4. Size data such as number of residential and saleable lots, typical lot size, parks and playground and open spaces.Any of the following registered and licensed professional: a. Environmental Planner b. Architect who is also an Environmental Planner, or c. Civil Engineer who is also An Environmental Planner, or d. Geodetic Engineer who is also an Environmental Planner, or e. Architect or a Civil Engineer or a Geodetic Engineer and an Environmental Planner as co-signatory
Plans specifications, bill of materials and cost estimates duly signed and sealed by the appropriate licensed professionals (1 original / set)Licensed and Registered Sanitary Engineer or Civil Engineer
Vicinity Map indicating the adjoining land uses, access roads, as well as existing facilities and utilities at least within 500 meters from the property boundaries of the project, drawn to any convenient scale duly signed and sealed (1 original / set)Registered and Licensed Geodetic Engineer
Topographic Plan duly signed and sealed (1 original / set)Registered and Licensed Geodetic Engineer
Survey Plan of the lot(s) as describe in TCT(s) duly signed and sealed (1 original / set)Registered and Licensed Geodetic Engineer
Certified True Copy of Title/s (1 original / set)Register of Deeds
Certified True Copy Latest Tax Declaration covering the property/ies subject of the application (1 original / set)City Assessor’s Office
Latest Tax Clearance (1 original / set) Tax receiptCity Treasurer’s Office
Right to use or deed of sale of right-of-way for access road and other utilities when applicable, subject to just compensation for private land (1 original / set)Applicant
Civil and Sanitary Works Design Engineering Plans/ construction drawing based on applicable engineering code and design criteria to include the following: 1. Road (geometric and structural) Design / Plan duly signed and sealed (2 original / set) 2. Storm Drainage and Sanitary Sewer System duly signed and sealed (2 original / set) Site Grading Plan (2 original / set)Licensed and Registered Civil Engineer; Licensed and Registered Sanitary Engineer or Civil Engineer; Licensed and Registered Civil Engineer
Water System Layout and Details duly signed and sealed Should a pump motor has a horsepower (hp) rating of 50 hp or more, its pump rating and specifications duly signed and sealed by (2 original / set)Licensed and Registered Sanitary Engineer or Civil Engineer; Licensed and Registered Professional Mechanical Engineer
Certificate of Service Coverage from the local water district or local franchise holder for water supply, whichever is applicable, or a Permit to drill duly approved by NWRBWater Utility Provider / National Water Resources Board
a. Electrical Plan duly signed and sealed (2 original / set)Licensed Professional Electrical Engineer
Certificate of Service Coverage from the local power distribution utility company or electric cooperativePower Utility Provider
Zoning Certificate (1 photocopy / set)City Planning and Development Office – Zoning Section
Certified true copy of DAR Conversion OrderDepartment of Agrarian Reform
Traffic impact assessments (TIA) for subdivision projects 30 hectares and above (1 original / set)Consultants / Traffic Engineer / Traffic Planner
Certified true copy of Environmental Compliance Certificate (ECC) or Certificate of Non-Coverage (CNC), whichever is applicable (1 original / set)Department of Environment and Natural Resources – Environmental Management Bureau
Project description (2 original /set): a. Project profile indicating the cost of raw land and its development (total project cost), amortization schedule, sources of financing, cash flow, architectural scheme, if any, and work program; b. Audited financial statement for the last 3 preceding years; c. Income Tax Return for the last three (3) preceding years; d. Certificate of registration with Securities and Exchange Commission (SEC); e. Articles of incorporation or partnership; f. Corporation by-laws and all implementing amendments, and For new corporations (3 years and below) statement of capitalization and sources of income and cash flow to support work programApplicant
List of names of duly licensed professionals who signed the plans and other similar documents in connection with the application filed with the city indicating the following information: b. Full Name (Surname, First Name, Middle Name and Maiden Name, in case of married women professional) c. Professional license number, date of issue and expiration of its validity; and d. Professional tax receipt and date of issue, and Taxpayer’s Identification Number (TIN)Applicant
Whenever applicable, copy of the special/temporary permit from the Professional Regulation Commission (PRC) and of the separate permit from the Department of Labor and Employment (DOLE) for Foreign Architects who signed on plans required under the IRR of PD 957Professional Regulation Commission Department of Labor and Employment
Additional Requirements for Application of Memorial Park / Cemetery: Landscaping plan indicating plant/tree species and other natural/man-made landscaping features e.g. lagoon, garden, benches, etc. duly signed and sealed (1 original / set)Licensed and Registered Landscape Architect
Centralized or combined storm and sewer system (1 original / set)Licensed and Registered Sanitary Engineer or Civil Engineer
Summary of Project Study indicating market, source/s of fund, statement of income, cash flow and work programApplicant
Clearances/Permits: (1 original / set) a. Clearance stating that the memorial park/cemetery is not located on ground where the water table is not higher than 4.50 meters below the ground surface. b. Water permit whenever a well within the project site shall be dug. Permit to operate the wellNational Water Resources Board (NWRB)
Permit, when necessary, e.g. when opening an access to a controlled traffic arteryDepartment of Public Works and Highways (DPWH)
Initial ClearanceDepartment of Health
Joint affidavit of owner/developer and licensed environmental planner that the memorial park/cemetery plan conforms to the standards and requirements of the rules and that development thereof shall be made in accordance with the program submitted to the city concernedApplicant

Steps

What you doWhat the office doesFeeTime
Submit application in 2 sets of complete documentary requirements at Zoning Section *Wait for the processing of the permitConduct initial evaluation of submitted documentary requirements as to completeness and receive; 1.1 Conduct of site inspection. Evaluate submitted requirements and prepare inspection and evaluation report in accordance with applicable laws. If found compliant, proceed to step 1.3; 1.2 Conditional Steps: * If with lacking requirements after inspection and evaluation, prepare and issue notice of deficiency for to be complied within 15 days subject to review and evaluation for 5 days *Failure to submit deficiency in requirements within 15 days, application will be denied without prejudice to submit a new application or request for reasonable period of extension.; 1.3 Review and recommend approval of evaluation report; 1.4 Approve evaluation report; 1.5 Endorse the application with the evaluation report to the Office of the Secretary to the Sanggunian; 1.6 For application with SP resolution, prepare Development Permit and Stamp approved Plans; 1.7 Review and countersign on Development Permit and Stamped plans; 1.8 Review, affix initials on the permit and sign approved plans; 1.9 Endorse the permit and stamped plans to the Office of the City Mayor for approval (Admin Aide VI CPDO; Zoning Officer I CPDO; Zoning Officer I CPDO; Zoning Officer III CPDO; CPDC CPDO; Admin. Aide VI CPDO; Admin Aide III CPDO; Zoning Officer III CPDO; CPDC CPDO; Admin Aide VI CPDO)None1 hour; 11 days; 4 hours; 3 days; 1 day; 2 hours; 1 day; 1 day; 1 day; 4 hours & 40 minutes
Receive Order of PaymentPrepare, notify and issue Order of Payment and direct client to the City Treasurer’s Office for the assessment and payment of fees (Admin Aide VI CPDO)Annex 01 HLURB Schedule of Fees30 minutes
Secure priority number at queuing machineProvide priority number from the queuing machine (Clerk CTO)–5 minutes
Wait for the number to be called to pay assigned fees at the City Treasurer’s Office – Window 3-5 *Make sure to secure Official Receipt that will be issued upon paymentAccept payment based on the Order of payment and issue the Official Receipt (Revenue Collection Clerk III CTO)–1 hour
Return to CPDO, present Official Receipt; 3.1 Receive the approved Development Permit and plans *Make sure to sign the logbook upon receipt of permitVerify and record the official receipt; 3.1 Release Development Permit and approved plans and advice client to sign the logbook (Admin Aide III CPDO)None30 minutes